Safeguarding energy transmission in the South Caucasus

Description

As part of the FC measure, a fundamental rehabilitation of the 220kV Gyumri 2 substation was carried out to eliminate a major weakness in the Armenian 220kV transmission network. The facility located in the north-west of the country was built in 1972, severely damaged by an earthquake in 1988, and restored only in a makeshift manner in 1992, which meant its safe and reliable operation was no longer guaranteed.

Overall rating: 3

Is based on:

Relevance: 2
Effectiveness: 3
Efficiency: 3
Impact: 3
Sustainability: 2

Evaluation criteria & rating scale

­

Country:Armenia
Sector:Energy
Budget funds

Federal budget funds that are passed on to partners by KfW Entwicklungsbank in the form of grants and interest rate reductions for loans. These do not have to be repaid.

:
7.300.000 €
Total funds

Funds that KfW raises on the capital market and then passes on to partners as a loan. The loan must be repaid.

:
14.600.000 €
Year of project completion:
2016

Notes on the methods

Download PDF

More on the topic